VANCOUVER LANDFILL DEMOLITION FIRE
Fighting The Fire
The
fire was discovered at approximately 2:00 p.m. on October 18.
Although no flames were visible when the fire was discovered,
an area of approximately 50 square metres had settled approximately
60 cm and smoke was venting from the area. Steam vents were previously
noted throughout the 700 by 80 metre demolition
area. With the discovery of the fire, there was concern
that the steam vents indicated fires were also present in other
areas of the demolition cell since various authors have reported
that landfill fires may exist without any external evidence of
the fire (Ettala et al., 1996;
Carpenter, 1996, Herold, 1999)
Within
two hours of the discovery of the fire, Poschner Construction
(the City’s onsite contractor) was delivering water to the fire
in three off-road dump trucks with delivery capabilities of 20,000
litres per load. The trucks are normally used at
the landfill to deliver cover material. In the event
of a fire the trucks can be quickly outfitted with a tailgate
to allow them to haul water. Water is supplied to the trucks via
an overhead delivery system feeding from an on-site dredge pond.
The trucks can be filled in about 3 minutes.
Because
the demolition material is essentially free draining and the surface
area where the fire was located was essentially flat, large quantities
of water could be applied without reducing trafficability in the
area or creating a risk of slope failure. By the end of the evening
of the 18th, approximately 800,000 litres of water
had been delivered to the area of the fire.
Off-road
dump trucks continued to deliver water to the area of the fire
and other hot spots within the demolition area on the 19th
and 20th. By the end of the 20th,
the water trucks had delivered a total of more than 2,000,000
litres of water.
2
. Poschner Construction
Off Road Truck,
20,000 litres per load.
|